Completed

  • [icon type=”chevron-circle-right” class=”accent fa-li”]Sep 30: Final move of our multi-tenanted environment. All Citrix and Email servers brought up with no issues. All systems running by 7:00 pm.
  • [icon type=”chevron-circle-right” class=”accent fa-li”]July 25: First Client’s servers successfully moved to new data center. No issues encountered during the move.. Planned move time was 7:30 pm to 11:30 pm. All systems running by 10:30 pm.
  • [icon type=”chevron-circle-right” class=”accent fa-li”]July 20: Omega Drive successfully moved to new data center. No issues encountered during the move. Planned move time was 5:00 pm to 9:00 pm. Service restored at 8:00 pm.
  • Planned move time was 5:00 pm to 9:00 pm. Service restored at 8:00 pm.
  • [icon type=”chevron-circle-right” class=”accent fa-li”]July 18: Move final Replibit Management Console to new data center
  • [icon type=”chevron-circle-right” class=”accent fa-li”]July 11: Transferred all hosted DNS to AWS. No client impact
  • [icon type=”chevron-circle-right” class=”accent fa-li”]July 4: All servers fully replicated to new data center with Veeam
  • [icon type=”chevron-circle-right” class=”accent fa-li”]June: Move Datto Backup Nodes from old to new data center, confirm that all client appliances are replicating to new location
  • [icon type=”chevron-circle-right” class=”accent fa-li”]June: Move Replibit Vault from old to new data center, confirm that all client appliances are replicating to new location
  • [icon type=”chevron-circle-right” class=”accent fa-li”]June: Test server recoverability at new data center, successful restores
  • [icon type=”chevron-circle-right” class=”accent fa-li”]May: Started converting backup solution at existing data center to Veeam and replicating to new data center
  • [icon type=”chevron-circle-right” class=”accent fa-li”]April: Installed new equipment in rack and tested basic functionality
  • [icon type=”chevron-circle-right” class=”accent fa-li”]March: Purchased new Servers, SAN and switches
  • [icon type=”chevron-circle-right” class=”accent fa-li”]February 2017: Acquired new data center location in Markham